The Artima Developer Community
Sponsored Link

.NET Buzz Forum
Estimation and Scheduling of Work

0 replies on 1 page.

Welcome Guest
  Sign In

Go back to the topic listing  Back to Topic List Click to reply to this topic  Reply to this Topic Click to search messages in this forum  Search Forum Click for a threaded view of the topic  Threaded View   
Previous Topic   Next Topic
Flat View: This topic has 0 replies on 1 page
Ashvil

Posts: 36
Nickname: ashvil
Registered: Aug, 2004

Ashvil is software professional looking for the next set of challenges. - http://Ashvil.net
Estimation and Scheduling of Work Posted: Nov 7, 2004 8:50 PM
Reply to this message Reply

This post originated from an RSS feed registered with .NET Buzz by Ashvil.
Original Post: Estimation and Scheduling of Work
Feed Title: Ashvil's Blog
Feed URL: http://ashvil.net/cs/blogs/blog/rss.aspx
Feed Description: Notes from the software world
Latest .NET Buzz Posts
Latest .NET Buzz Posts by Ashvil
Latest Posts From Ashvil's Blog

Advertisement

One of the reasons projects spin out of control is poor estimation and scheduling of work. There have been tons of material on estimation but scheduling has not got the same coverage.

 

One of the common pitfalls of scheduling is mapping a project plan estimated numbers to a team member at 40 hours a week. Let’s run though this with an example, John is working on a 6 month project that is assuming that he would be working for 40 hours a week for the next six months. Besides working on this project, John has to attend a regular staff meeting, take care of some production support issues, take part in a virtual team for planning, attend some training and mentor a new employee. Also, John is planning to take three days off around Thanksgiving to spend the week with his family.

 

End result is that John this month can spend only 25 hours week on an average on this project but the project manager has gone ahead and budgeted at John to spend 40 hours a week. Poor scheduling like this that does not take care of the actual number of hours that a team member can commit and ignores vacation and holiday times are doom their projects to failures. If your project plan is based on inaccurate data, how on earth do you expect to ship on time.

 

There is a simple solution to this – Always plan with the correct numbers of hours a team member can spend and include vacation/holidays/buffer time.

Read: Estimation and Scheduling of Work

Topic: UK Architect Forum - Software Tools and Methods Previous Topic   Next Topic Topic: It's been awhile

Sponsored Links



Google
  Web Artima.com   

Copyright © 1996-2019 Artima, Inc. All Rights Reserved. - Privacy Policy - Terms of Use